Last week, Clifton Intersection Safety Improvement Project crews excavated the roadway on I-70B and F 1/2 Road to reinforce it with geogrid to accommodate heavy truck traffic coming out of Central Distributing Co., 3244 F 1/2 Road.
Crews cover reinforcement layers with a 3/4" road base. |
Crews continue to install storm drain inlets and culverts on the east side of I-70B and F 1/2 Road in Clifton. |
Construction crews plan on pouring sidewalks, curb and gutter on the west side of I-70B on F 1/2 Road by the end of this week. |
Crews install electrical conduit and pull boxes that will connect to the future signal light on I-70B and F 1/2 Road in Clifton. |