The project aims to add a 6-foot shoulder on the north side of South Broadway between Rado Drive and Desert Hills Road, replace an existing Redlands water and power irrigation culvert, complete approximately 1000 feet of 8-foot sidewalk segments on the south side, and make intersection improvements to Spoon Court including a new pedestrian cross-walk and signage.
Mesa County and the City of Grand Junction will split the project costs evenly, and Mesa County will operate the project.
To watch the approval of the contract at the Nov. 8 administrative public hearing, visit https://bit.ly/3NytWRn.